  • TOWN OF NANTUCKET, MASSACHUSETTS SURFSIDE ROAD AREA SEWER SYSTEM IMPROVEMENTS PROJECT

    Mon. 6/7

    • James Lydon – sidewalk blocking at 21 Main St (and N Cambridge St) for roofing
    • Atlantic Aeolus modular move – 134 Old South Rd to 2 Grey Lady Ln:  Route:  Old South Rd, Fairgrounds Rd, Surfside Rd, Bartlett Rd, Grey Lady Ln
     
    Mon. 6/7 – Thurs. 6/11
    • Robert B. Our - SURFSIDE ROAD SEWER IMPROVEMENTS PROJECT, 4pm to 2am, Mon – Thurs. The road will be totally blocked and detours will be in place. See attached “Weekly Schedule Update #10” and updated detour map.
     
    Mon. 6/7 – Fri. 6/11
    • CC Construction – Old South Rd at the 2 Fairgrounds Rd entrance – “we have no work next week which will affect traffic on Old South Road.  We will be working on road shoulder area only.”
    • Evergreen Landscaping – partial blocking at 14 Straight Wharf for CATV
    • Evergreen Landscaping – partial blocking at 37 Straight Wharf for CATV
    • KOBO partial blocking – Madaket Rd & M Street for drainage repair
    • Victor-Brandon - partial blocking at N Cambridge St at Madaket Marine entrance for milling and overlay
    • Victor-Brandon - partial blocking at entrance of Lifesaving Museum off Polpis Rd for paving
     
    Tues. 6/8
    • Structures Unltd shed move – 17 Nancy Ann Ln to 1 Wamasquid Pl. ROUTE:  Old South Rd, Milestone Rotary, Sparks Ave, Surfside Rd, Vesper Ln, Hummock Pond Rd, Hussey Farm Rd, Pond Rd, Meadow View Rd, Wamasquid Pl
     
    Wed. 6/9 – Thurs. 6/10
    • Warren Ard House Move – 31 Fairgrounds Rd to 33 South Shore Rd. ROUTE:  Fairgrounds Rd, South Shore Rd. (Thurs. 6/10 is the rain date)
     
    Wed. 6/9 – Sun. 6/13
    • Jeffrey Haines – partial blocking (parking spaces) on Washington St for 12 Main St Rear Courtyard for truck unloading
     
    Fri. 6/11
    • SURFSIDE ROAD SEWER IMPROVEMENTS PROJECT, 9am to 2pm for paving. The road will be totally blocked and detours will be in place. See attached three-week look-ahead.
     Weekly Construction Hours:  Monday-Thursday evenings: 4pm-2am Fridays: 9am-2pm (trench paving)

    Current Road Closures:
    Monday-Thursday evenings: Full road closure between Bartlett Rd. and First Way Fridays: Single lane closure during trench paving activities

    One Week Look Ahead (6/7 thru 6/11)

    • Monday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road from Maclean Lane towards First Way

    • Friday:
    o Trench paving

    Two Week Look Ahead (6/14 thru 6/18)

    • Monday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road from Tashama Lane/Washaman Ave. towards First Way

    • Friday:
    o Trench paving

    Three Week Look Ahead (6/21 thru 6/25)

    • Monday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road from First Way towards Vesper Lane

    • Friday:
    o Trench paving

    Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations. 
     

  •