• Nantucket Island Chamber of Commerce to co-host Retail Marijuana Forum

  • TOWN OF NANTUCKET CONSTRUCTION SCHEDULE – WEEKLY UPDATE

    Mon. 5/17 – Tues. 5/18

    • CC Construction – partial street and sidewalk blocking of Old South Rd to install electric/water to medians at Richmond – See Richmond 3-week look-ahead
     
    Mon. 5/17 – Wed. 5/19
    • Barrett Enterprises – total blocking of New Mill St for sewer main replacement, sewer line install
     
    Mon. 5/17 – Thurs. 5/20
    • Robert B. Our - SURFSIDE ROAD SEWER IMPROVEMENTS PROJECT, 4pm to 2am, Mon – Thurs. The road will be totally blocked and detours will be in place. See attached three-week look-ahead.
     
    Mon. 5/17 – Fri. 5/21
    • Stojanov Inc – partial street blocking and sidewalk blocking – 17 Main St (& S Water St side)
    • CC Construction - Old South Rd on the shoulder at the 2 Fairgrounds Rd entrance partially blocked for new bus pull-off & sidewalk install
    • ACK Marine – partial street (parking spaces) and total sidewalk blocking – 21-27 Easy St (Land Bank park construction)
    • Blue Flag Const – 3 parking spaces at 29 Centre St
    • 11 India St LLC – partial sidewalk blocking at 29 Centre St (approx. once per week)
    • KOBO – partial blocking at Easton St/S Beach St intersection to repair broken pipe & repair sink hole
    • KOBO – partial blocking on Orange St at Cherry St for catch basin/sink hole repair
    • KOBO – partial blocking of Madaket Rd at F St intersection/total blocking on bike path for leaching basin
    • Victor-Brandon – partial blocking – PAVING OF OLD SOUTH RD AT RICHMOND and INTERSECTION AT AIRPORT RD & ASSOCIATED WORK – See Richmond 3-week look-ahead
     
    Tues. 5/18
    • Atlantic Aeolus Modular Move – SSA to 22 Cannonbury Ln, Sconset. Route:  Broad St, South Water St, Washington St, Francis St, Union St, Orange St, Milestone Road, Morey Ln, Low Beach Rd, Cannonbury Ln
     
    On Tues. 5/18 – Wed. 5/19
    • CC Construction will be “doing the water main connection on Tuesday 05/18 and Wednesday 05/18/2021.  This will mean police detail and alternating traffic at the 2 fairgrounds driveway entrance on Old South Road.”

    Thurs. 5/20
    • Atlantic Aeolus Modular Move – SSA to 22 Cannonbury Ln, Sconset. Route:  Broad St, South Water St, Washington St, Francis St, Union St, Orange St, Milestone Road, Morey Ln, Low Beach Rd, Cannonbury Ln
     
    Fri. 5/21
    • SURFSIDE ROAD SEWER IMPROVEMENTS PROJECT, 9am to 2pm for paving. The road will be totally blocked and detours will be in place. See attached three-week look-ahead.
     
    The Sewer Dept. has received a waiver from the Select Board for night work to repair broken sewer manhole frames and covers at Washington St at Meader St, and at ^ Prospect Street. There will be associated street closures and the work is scheduled for this week – 5/17 – 5/20. 
     
    KOBO is done with Madaket at F Street, but is starting at North Beach St at Easton St to repair another sinkhole. – Mon – Fri.
     
    Sewer Dept  blocked one outbound lane on Prospect St between Joy and Milk for a short time this morning in order to CCTV the line before they start work tonight.
     
    Victor-Brandon paves the bike lane on Orange St between the Rotary and East Creek Rd, Wed. 5/19 & Thurs. 5/20.

    Weekly Construction Hours:   Monday-Thursday evenings: 4pm-2am Fridays: 9am-2pm (trench paving)

    Current Road Closures:
    Monday-Thursday evenings: Full road closure between Bartlett Rd. and Miacomet Ave. Fridays: Single lane closure during trench paving activities

    One Week Look Ahead (5/17 thru 5/21)

    • Monday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road from #38 Surfside towards Bartlett Road

    • Friday:
    o Trench paving

    Two Week Look Ahead (5/24 thru 5/28)

    • Monday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road into Bartlett Road intersection – Switch to Phase 2 road closure and detour once crew is north of Bartlett Road

    • Friday:
    o Trench paving

    Three Week Look Ahead (6/1 thru 6/4)

    • Monday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road from Bartlett Road towards First Way – Phase 2 road closure and detour in place

    • Friday:
    o Trench paving