• Nantucket Island Chamber of Commerce to co-host Retail Marijuana Forum

  • TOWN OF NANTUCKET, MASSACHUSETTS SURFSIDE ROAD AREA SEWER SYSTEM IMPROVEMENTS PROJECT

    Mon. 5/31

    • 11 India St LLC – partial sidewalk blocking at 29 Centre St (approx. once per week)
     
    Mon. 5/31 – Thurs. 6/3
    • Robert B. Our - SURFSIDE ROAD SEWER IMPROVEMENTS PROJECT, 4pm to 2am, Mon – Thurs. The road will be totally blocked and detours will be in place. See attached “Weekly Schedule Update #9” and updated detour map.
     
    Mon. 5/31 – Fri. 6/4
    • CC Construction – partial blocking of Old South Rd on the shoulder at the 2 Fairgrounds Rd entrance for new bus pull-off & sidewalk install
    • James Lydon – sidewalk blocking at 21 Main St (and N Cambridge St) for roofing
     
    Tues. 6/1 – Wed. 6/2
    • Warren Ard OTR – 31 Fairgrounds Rd to 6 Monohansett Rd. ROUTE:  Fairgrounds Rd, Surfside Rd, Boulevarde, Lovers Ln, Okorwaw Ave, Monohansett Rd (Wed. 6/2 is the rain date) 
    • Victor-Brandon – partial blocking of Old South Rd on the shoulder at the 2 Fairgrounds Rd to pave new bus pull-off & sidewalk
     
    Tues. 6/1 – Thurs. 6/3
    • Victor Brandon – partial blocking on Orange St between Milestone Rotary & East Creek Rd for bike lane work
     
    Tues. 6/1 – Fri. 6/4
    • KOBO partial blocking – Madaket Rd & M Street for drainage repair
     
    Wed. 6/2 – Thurs. 6/3
    • Nantucket Oasis Pool & Spa – partial blocking (parking spaces) at 103 Main St for concrete/pump trucks
    • Sewer Dept – total blocking of York St between Orange & Pleasant Streets for sewer repairs
     
    Thurs. 6/3
    • Atlantic Aeolus Modular Move – SSA to 4 Seven Mile Ln. Route:  Broad St, South Water St, Washington St, Francis St, Union St, Orange St, Milestone Rd, Seven Mile Ln
     
    Fri. 6/4
    • Atlantic Aeolus Modular Move – SSA to 5 Bartlett Rd via Larrabee Ln. Route:  Broad St, South Water St, Washington St, Francis St, Union St, Orange St, Old South Rd, Fairgrounds Rd, Surfside Rd, Larrabee Ln
     
    • SURFSIDE ROAD SEWER IMPROVEMENTS PROJECT, 9am to 2pm for paving. The road will be totally blocked and detours will be in place. See attached three-week look-ahead.
    Weekly Construction Hours:   Tuesday-Thursday evenings: 4pm-2am Fridays: 9am-2pm (trench paving)

    Current Road Closures:
    Tuesday-Thursday evenings: Full road closure between Bartlett Rd. and First Way Fridays: Single lane closure during trench paving activities

    One Week Look Ahead (6/1 thru 6/4) ** NO WORK MONDAY **

    • Tuesday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road from Bartlett Road towards First Way
    **Phase 2 Road Closure and Detour in place**

    • Friday:
    o Trench paving

    Two Week Look Ahead (6/7 thru 6/11)

    • Monday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road from Maclean Lane towards First Way
    **Phase 2 Road Closure and Detour in place**

    • Friday:
    o Trench paving

    Three Week Look Ahead (6/14 thru 6/18)

    • Monday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road from Washaman Ave towards First Way
    **Phase 2 Road Closure and Detour in place**

    • Friday:
    o Trench paving

    Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations.

  •