  • TOWN OF NANTUCKET, MASSACHUSETTS SURFSIDE ROAD AREA SEWER SYSTEM IMPROVEMENTS PROJECT

    Mon. 5/24
    • Atlantic Aeolus - partial blocking at 30 Cliff Rd to remove steel from under a house, 10am to 4pm
    • TCE – partial blocking at 6 Thurstons Way for sewer connection
    • Atlantic Aeolus modular move – SSA to 57 Pochick St. ROUTE:  Broad St, South Water St, Washington St, Francis St, Union St, Orange St, Old South Road, Fairgrounds Rd, Surfside Rd, Boulevarde, Pochick Ave
     
    Mon. 5/24 – Wed. 5/26
    • Stojanov Inc – partial street blocking and sidewalk blocking – 17 Main St (& S Water St side)
    • Barrett Enterprises – total blocking of Mill St for 23 Prospect St for sewer & water tie-in
     
    Mon. 5/24 – Thurs. 5/27
    • Robert B. Our - SURFSIDE ROAD SEWER IMPROVEMENTS PROJECT, 4pm to 2am, Mon – Thurs. The road will be totally blocked and detours will be in place. See attached “Weekly Schedule Update #8”.
    • Blue Flag Const – 3 parking spaces at 29 Centre St
     
    Mon. 5/24 – Fri. 5/28
    • CC Construction - Old South Rd on the shoulder at the 2 Fairgrounds Rd entrance partially blocked for new bus pull-off & sidewalk install – see attached “Three Week Look Ahead Schedule – Waitt Drive”
    • James Lydon – sidewalk blocking at 21 Main St (and N Cambridge St) for roofing
    • 11 India St LLC – partial sidewalk blocking at 29 Centre St (approx. once per week)
    • KOBO – partial blocking on Orange St at Cherry St for catch basin/sink hole repair
    • Victor-Brandon – partial blocking – PAVING OF OLD SOUTH RD AT RICHMOND and INTERSECTION AT AIRPORT RD & ASSOCIATED WORK – See Richmond 3-week look-ahead – STARTING MONDAY!! Seek alternate routes if possible!
    • ACK Marine will continue to have the sidewalk and parking spaces blocked on Easy St while they work on the Land Bank park
      Tues. 5/25 
    • The Sewer Dept. plans to block one lane of traffic at 6 Prospect St tomorrow at 9:00 AM to pave the patch from the work done last week.
    • TCE’s permits for 6 Thurstons Way has been extended through Tues. 5/25
    Tues. 5/25 – Wed. 5/26
    • Nantucket Oasis Pool & Spa – partial blocking (parking spaces) at 103 Main St for pool excavation
    • Atlantic Aeolus OTR – 105 Tom Nevers Rd to 10 Tom Nevers Rd. ROUTE:  Tom Nevers Rd. (Wed. 5/26 is the rain date)
    Wed. 5/26
    •  Surfside Sewer Project - intersection at Surfside Rd and Bartlett Rd will be completely closed tonight Surfside Sewer Project
     
    Thurs. 5/27
    • Atlantic Aeolus Modular Move – SSA to 65 Cato Ln. Route:  Broad St, South Water St, Washington St, Francis St, Union St, Orange St, Old South Rd, Fairgrounds Rd, Surfside Rd, Bartlett Rd, Cato Ln
    • KOBO total blocking of India St between Center St & Federal St starting at 11:00 PM through 6:00 AM on Fri. 5/28 for environmental cleanup with Clean Harbors & NGrid
    • CC Construction will have Rugged Rd totally blocked on Thurs. 5/27 to install a new fire service line for Nantucket Lighthouse School.
     
    Fri. 5/28
    • SURFSIDE ROAD SEWER IMPROVEMENTS PROJECT, 9am to 2pm for paving. The road will be totally blocked and detours will be in place. See attached three-week look-ahead.
    • Barrett Enterprises permits for Mill St/23 Prospect St has been extended through Fri. 5/28
    • Toscana will have Orange St partially blocked tomorrow at #14 for a concrete and pump trucks.
    Weekly Construction Hours: Monday-Thursday evenings: 4pm-2am Fridays: 9am-2pm (trench paving)

    Current Road Closures: Monday-Thursday evenings: Full road closure between Bartlett Rd. and Miacomet Ave. Fridays: Single lane closure during trench paving activities

    One Week Look Ahead (5/24 thru 5/28)

    • Monday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road from #34 Surfside into intersection of Surfside Rd. & Bartlett Rd. **Intersection of Surfside Rd. & Bartlett Rd. blocked Wednesday**
    o Commence force main installation in roadway between pump station site (near Windy Way) and Miacomet Ave.

    • Friday:
    o Trench paving

    Two Week Look Ahead (6/1 thru 6/4)

    • Monday thru Thursday:
    o Complete force main installation to Miacomet Ave.
    o Continue installation of gravity sewers, progressing north on Surfside Road from Bartlett Road towards First Way
    **Phase 2 Road Closure and Detour in place**

    • Friday:
    o Trench paving

    Three Week Look Ahead (6/7 thru 6/11)

    • Monday thru Thursday:
    o Continue installation of gravity sewers, progressing north on Surfside Road towards First Way

    • Friday:
    o Trench paving

    Please note that this is a projected schedule and will be adjusted accordingly based on Contractor’s actual progress and potential weather cancellations. 
     

  •